UPDATE MAY 2021

Council undertook a second round of community consultation from 27 August 2020 to 27 September 2020 regarding the proposed raised pedestrian crossings as part of Stage 2. All proposals generally received strong support from the community and were subsequently approved by the Traffic Committee. The community engagement outcomes report can be viewed here.

In addition, Council received additional funding in 2020/21 from Transport for NSW under the Federal Stimulus Road Safety Program to complete sites 18C and 20.

Works on Stage 2 pedestrian crossings commenced in April 2021. Construction on all the pedestrian crossings is scheduled to be completed by 30 June 2021.

Site ID

Location

Description of treatment

View Plan

1

Clark Road at McDougall Street

Raised pedestrian crossing

Site 1 plan

4

Broughton Street at Willoughby Street

Raised pedestrian crossing

Site 4 plan

18C

Fitzroy Street at Alfred Street South

Raised pedestrian crossing

Site 18C plan

20

Broughton Street at Kirribilli Avenue

Raised pedestrian crossing

Site 20 plan


Share UPDATE MAY 2021 on Facebook Share UPDATE MAY 2021 on Twitter Share UPDATE MAY 2021 on Linkedin Email UPDATE MAY 2021 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>