UPDATE JUNE 2020
The funding agreement with Transport for New South Wales (TfNSW) was subject to the construction works for this project to be finalised by 30 June 2020, however due to the outcomes of the consultation requiring changes to the original scheme as endorsed by Council, the detailed design and tender process was delayed.
Council and TfNSW agreed to separate the project into two stages. The delivery date for Stage 1 was extended to 28 August 2020. Construction works for Stage 1 began 22 June 2020. Council is undertaking detailed design for Stage 2. Stage 2 construction will be undertaken after site specific community consultation is completed.
Stage 1:
Site ID |
Location |
Description of treatment |
2 |
Broughton Street |
Raised threshold - full road width |
5 |
Hipwood Street |
Flush threshold treatment |
7 |
McDougall Street |
Flush threshold treatment |
8 |
Burton Street |
Raised pedestrian crossing |
9 |
Bligh Street |
Continuous footpath treatment |
10 |
Pitt Street |
Continuous footpath treatment |
11 |
Paul Street |
Continuous footpath treatment |
14 |
Alfred Street South |
Raised threshold - full road width |
16 |
Alfred Street South |
Flush threshold treatment |
17 |
Lavender Street |
Flush threshold treatment |
18A |
Alfred Street South |
Raised pedestrian crossing – To be constructed with Stage 2 works |
19 |
Glen Street |
Continuous footpath treatment |
Stage 2:
Site ID |
Location |
Description of treatment |
1 |
Clark Road |
Raised pedestrian crossing |
4 |
Broughton Street |
Raised pedestrian crossing |
18C |
Fitzroy Street |
Raised pedestrian crossing |
20 |
Broughton Street |
Raised pedestrian crossing |
Consultation has concluded