UPDATE JUNE 2020

The funding agreement with Transport for New South Wales (TfNSW) was subject to the construction works for this project to be finalised by 30 June 2020, however due to the outcomes of the consultation requiring changes to the original scheme as endorsed by Council, the detailed design and tender process was delayed.

Council and TfNSW agreed to separate the project into two stages. The delivery date for Stage 1 was extended to 28 August 2020. Construction works for Stage 1 began 22 June 2020. Council is undertaking detailed design for Stage 2. Stage 2 construction will be undertaken after site specific community consultation is completed.

Stage 1:

Site ID

Location

Description of treatment

2

Broughton Street

Raised threshold - full road width

5

Hipwood Street

Flush threshold treatment

7

McDougall Street

Flush threshold treatment

8

Burton Street

Raised pedestrian crossing

9

Bligh Street

Continuous footpath treatment

10

Pitt Street

Continuous footpath treatment

11

Paul Street

Continuous footpath treatment

14

Alfred Street South

Raised threshold - full road width

16

Alfred Street South

Flush threshold treatment

17

Lavender Street

Flush threshold treatment

18A

Alfred Street South

Raised pedestrian crossing – To be constructed with Stage 2 works

19

Glen Street

Continuous footpath treatment


Stage 2:

Site ID

Location

Description of treatment

1

Clark Road

Raised pedestrian crossing

4

Broughton Street

Raised pedestrian crossing

18C

Fitzroy Street

Raised pedestrian crossing

20

Broughton Street

Raised pedestrian crossing


Share on Facebook Share on Twitter Share on Linkedin Email this link